Copies of s.30 NEMA reports and/or directives relating to incident at Duvha Power Station.
Copies of the following records are requested:
1. In respect of the sulphur plant leakage at the Eskom Duvha Power Station towards the end of 2013 and the refurbishment thereof from about May 2014:
1.1. the initial report - apparently dated 26 May 2014 - compiled by Eskom relating to the nature of the incident, identifying any risks posed by the incident to public health, safety and property, the toxicity of substances or by-products released by the incident, and any steps taken by Eskom to avoid or minimise the effects of the incident on public health and the environment (section 30(3) of NEMA);
1.2. any directives issued by the DEA or other authorities in terms of section 30(6) and (7) of NEMA;
1.3. all evidence of any measures taken by the DEA and other authorities in terms of section 30(8) of NEMA; and
1.4. the DEA’s comprehensive report on the incident in terms of section 30(10) of NEMA, as well as any other authorities’ comprehensive reports in the DEA’s possession.
Initial request communication
Communication sent
Response received
Response date: 2014-11-06Response nature: Released in part
Received within statutory period: No