Records related to the development of the South African rail system.
Reference number: SAH-2013-TNT-0002
Submitting organisation: South African History Archive (SAHA)
Requestee: TRANSNET
Status: closed
Status note: Process concluded
Date submitted: March 12, 2013
Stage(s):
Initial request, internal appeal
Request description:
Any and all records related to but not limited to:
Procurement policies
Percentage spent infrastructure development on local versus import/international import (including labour costs and consulting fees)
Total budget allocated for the improvement of commuter and freight train network from 2011 to 2020 (including yearly increases)
Initial request communication
Communication sent
Submission of PAIA request SAH-2013-TNT-0002
Sent on: March, 12 2013
Response received
Response date: 2013-06-11Response nature: Deemed refusal
Received within statutory period: No
Internal appeal communication
Communication sent
Submission of internal appeal against decision relating to PAIA request SAH-2013-TNT-0002
Sent on: June, 11 2013
Failure to respond to internal appeal for PAIA request SAH-2013-TNT-0002 within statutory time frame
Sent on: August, 10 2013
Reminder to submit complaints to Chapter 9 institutions
Sent on: August, 30 2013
Response received
Response date: 2013-09-13Response nature: Substituted new decision - denied with grounds
Received within statutory period: No
Downloads